SAMARCO – Pipeline New “Booster” Station – Abre Campo – MG

Pumping Station.


SAMARCO – Infrastructure Project (earthwork, drainage, paving and urbanization) plant II – Germano – Mariana – MG

Beneficiation Plant.


SAMARCO – Slime Fine Recovery – Mariana – MG

Beneficiation Plant – 700,000 t/year of concentrate – Conceptual, basic and detailed engineering.


MINERAÇÃO TABOCA – Coarse Tailing Project (turn key) – Pitinga – AM

Beneficiation Plant – 6.5 Mtpy of feed – Conceptual, basic and detailed engineering.Design developed in partnership with Metso/Milplan/WEG for turn-key implementation of a Cassiterite (Tin) Coarse Tailings’ treatment facilities.


VOTORANTIM – Filtering and Storage / Shipment of concentrate project for the relocation of Usicon C – Vazante – MG

Beneficiation Plant – 440,000t / year – Basic and detailed engineering.


VOTORANTIM – Project for increasing the capacity of the recovery system of zinc and wastewater treatment – Três Marias – MG

Beneficiation Plant – increase capacity of the current treatment system from 13,500 m³/day to 18,500 m³/day.